MGE UPS Systems SineWave Installatievoorschrift En Handleiding pagina 75

Actieve harmonische compensator 20-480 a
Inhoudsopgave

Advertenties

installation
(cont.)
Connection operations:
Connection operations must be
carried out without the
conditioners being energized.
For the protection of persons,
remember that the PE or PEN
protective conductor must always be
connected first.
Earthing system: SineWave™ is suited
to all types of earthing system.
Procedure:
check that the lifting sling has been
removed;
check that the SineWave™ supply
circuit-breaker placed in your low
voltage switch cubicle is in open
position (O);
wiring is connected via the bottom, in
front of the conditioner;
to access the connection terminal
block, remove the front and lower
protection plates;
power connections are made on the
bolted terminal block;
the lower protection plate of the
power terminal block must be fitted with
bushings for cable feedthrough. If
several holes are made to feed the
cables through, cut a slot common to all
the holes to prevent eddy currents from
being generated;
connect the PE or PEN conductor
first;
connect the other conductors so that
they comply with the rotation direction
of the phases and the indications in the
figures opposite.
The connecting cables must be
mechanically fixed near the
terminal block so that any mechanical
stress on the conductors is prevented.
Note:
If there is traction on the cables, the PE
or PEN must be the last conductor
subject to its effects.
18
installation and operation manual of SineWave™: E-51027008XT/AD
front protection
plate
lower protection
plate
PE neutral
phase 1
phase 2
phase 3
MGE UPS SYSTEMS