Download Inhoudsopgave Inhoud Print deze pagina

Check Functionality Of Safety Devices; Gas Tightness Check; Boiler Shut Down - elco R600 Bedienings- En Installatiehandleiding

Inhoudsopgave

Advertenties

Beschikbare talen
  • NL

Beschikbare talen

  • DUTCH, pagina 68
Commissioning

Check functionality of safety devices

Gas tightness check

Boiler shut down

1
2 3
5
4
6
7
18
All manuals and user guides at all-guides.com
Check functionality of safety devices
All safety devices have to be checked
on good functioning. Safety devices on
a standard boiler are a water flow tem-
perature sensor, fluegas temperature
sensor, water flow switch minumum
gas pressure switch and ionisation
electrode. These devices can be
checked as described below.
Flow temperature sensor (1)
Disconnect the plug from the sensor
while the boiler is switched on. This
should result in a lockout no. 20.
The lockout should disappear as soon
as the plug is placed back in position,
the boiler will restart.
Return temperature sensor (2)
Disconnect the plug from the sensor
while the boiler is switched on. This
should result in a lockout no. 40.
The lockout should disappear as soon
as the plug is placed back in position,
the boiler will restart.
Flue gas temperature sensor (3)
Disconnect the plug from the sensor
while the boiler is switched on. This
should result in a lockout no. 28.
The lockout should disappear as soon
as the plug is placed back in position,
the boiler will restart.
.
Minimum gas pressure switch (5)
Close the gas cock when the boiler is in
standby position (
). Open the test
K
point on the gas line (4) while measur-
ing the gas pressure on the test point
of the gas pressure switch (5).
The boiler will go in lockout no. 2 when
the switch off setting is achieved. Close
both test points and open the gas cock.
Ionisation electrode (6)
Remove electrical connection from the
ionisation electrode while the boiler is
running, the boiler will go in lockout no.
128. The boiler will try to restart. With
the electrical connection removed, the
restart will result in lockout no. 133.
When the connection is already
mounted, the restart will be successful.
Measuring the ionisation current can
be done by mounting a multi-meter (set
to µA) in between the ionisation elec-
trode and its electrical connection. The
ionisation current should always be
above 1.2 µA, in normal conditions it
will be 6 µA and above.
Gas tightness check
Check the gas tightness of all sealed
connections with an approved soap or
electronic gas analyzer, for example:

Test points

Bolt connections

Gaskets of mixing system, etc.
Boiler shut down
When the boiler will not be used for
longer periods, shut down the boiler by
following procedure:

Switch the boiler in standby operation
(K)

Switch off the boiler with the on/off
switch (7)

Disable power supply to the boiler by
deactivating the mains isolator switch
in the boiler room

Close the gas supply to the boiler.

Advertenties

Inhoudsopgave
loading

Deze handleiding is ook geschikt voor:

R601R602R603R604R605R606 ... Toon alles

Inhoudsopgave