5
System commissioning
Always avoid the pumps running dry (air is drawn in) for a period of > 30 s. The pumps can become damaged.
Do not activate pumps in manual operation if the system tank is not filled to at least minimum level.
5.1
Open the shut-off valve
The shut-off valve was pushed in for transport.
Always open before putting into service!
5.2
Positions of the Ecolift FKA emergency closure lever
Position
Function
"OPEN"
Operating posi-
(lever in
tion
sewer-side
position)
„N"
Construction
(lever in cen-
phase position,
tral position)
pendulum posi-
tion
"CLOSED"
Pipe locking in
(lever in
the event of a
house-side
breakdown or
position)
decommission-
ing
5.3
Connect to the mains voltage
Establish mains voltage (400V control units)
Connect the mains cable to the mains power supply.
Move main switch (1) into ON position.
The first initialisation starts automatically.
The device checks the electrical components.
Voltage test of the standby batteries.
|3.10. Language|
Menu item
Establish mains voltage (230V control units)
Insert the safety plug into the designated socket.
Move main switch (1) into ON position.
The first initialisation starts automatically.
The device checks the electrical components.
Voltage test of the standby batteries.
|3.10. Language|
Menu item
010-694
Effect
The consumers connected can be drained and are
secured by the motor-driven backwater flap.
The consumers connected can be drained and are
secured against backwater by a flap. This non-
motor-driven condition as supplied is only suitable
for the drainage of faecal-free wastewater (e.g. dur-
ing the construction phase until commissioning has
taken place properly).
The building is secured in the best possible way
against water penetration; the consumers can be
drained.
is displayed.
is displayed.
Backwater lifting station / Installation and operating instructions
Side view
37 / 136