√ Check whether the cores have been properly tightened, see 19.3.
√ Check whether the ground connection has been made with the supplied
grounding.
√ Check whether the cable thickness of the power cable matches the fused
current rating.
√ Check whether the charging station is tightly and properly secured.
√ Check whether the station is sufficiently waterproof.
√ Keep the immediate environment of the work area free from obstacles.
Before the power is connected to the charging station, you must first call
Ecotap® B.V. on +31 (0)411 745 020 (Mo – Fr 09:00 to 16:00) so that we can
activate its software (this requires the unique charging station number).
19. OPERATING / INSTALLATION MANUAL
19.1 Open the door
The door can be opened in the following way.
Insert the key supplied and turn it until the handle unlocks.
Turn the handle so the door will unlock.
Carry out these steps in reverse to close and lock the door.
19.2 Mounting on the foundation
To fit the foundation, a hole must be dug of roughly L 750 mm x D 450 mm x
H 530 mm. The soil must be stable and levelled.
Place the foundation base level in the hole. The upper surface of the base
must be flush with the upper surface of the grade / paving. The foundation
must then be reinforced by adding at least two 20 kg bags of fast-setting
concrete in the corners of the foundation.
After the fast-setting concrete has cured, the charging station can be
mounted on its foundation using the nuts and bolts provided (nuts to the
top).
The hole in the foundation and the charging station must be lined up.
See drawing of the topview of the foundation base. Take account of the
connection face of the charging station in relation to walls, hedges, etc.
Always ensure that the doors are fully open!
Also keep in mind that there is sufficient space for the operation of the
charging station. For this we advise to keep at least 1 meter of free space
around the charging station.
20