CEILING INSTALLATION
ENY–P1–S / ENY–P2–S / ENY–P3–S
The ENERGY PLUS heat recovery unit comes
with 4 mounting brackets which can be used
together with vertical threaded rods or
suspension chains to facilitate fixing to the
ceiling and levelling. It is recommended to
install and fix the unit in the correct posi-
tion before making the connections to the
ducted system or condensate discharge pipe
(discharge side) and the electrical connec-
tions.
The ducted system must be secured indepen-
dently from the unit. Use the terminal block in
the Control Panel of the unit to make the con-
nections to the mains power supply.
ENY–P4–S
It is not advisable to hang the ENY P4 units
fromthe ceiling. If strictly necessary, the
unit must be supported from underneath
with structural elements and vertical rods
able to withstand its weight. When suppor-
ting the unit, make sure to leave sufficient
clearance for maintenance and removal of
the filters.
Vertical rod (not supplied)
M10
nut (not supplied)
Mounting bracket (included)
M10
serrated washer (not supplied)
FLOOR INSTALLATION
INSTALLATION ON MOUNTING
FEET
All the units are supplied with brackets as
standard, to be used for the floor installa-
tion of the unit.
x4
x4
x8
Mounting feet
A
2
1
3
B
1
2
3
Move the support (A) on the bottom of the
unit (1) using 4,2x13 mm screws (2) sup-
plied as standard.
Insert the foot (B) in the support (A);
block it by M10 nuts (3).
132
A
2
1
3
1
2
3
B