INSTALLATION

FIRST START-UP

9.3

Water connection

The fast connectors may be connected only to the bare
copper pipe (External Ø 15 mm).
4
1 Magnet valve
2 Fast connector (straight)
3 Fast connector (90°)
4 Temperature limiter (STB - steam)
» Assemble surface-mounted cold water delivery pipe and
insert in fast connector (90°) down to the stop (approx. 28
mm).
» Optional concealed connection: Remove fast connectors
straight and 90° and mount straight fast connector on cold
water connection.
Fitting a stopcock is recommended for servicing work.
Steam pipe installation
The condensation chamber prevents steam from escaping. On
malfunction, the steam must be removed by a pipe. The owner
must install a steam pipe for this purpose.
Risk of injury!
The steam pipe fitted by the customer may not be sealed
off! If a drain funnel is used, the steam pipe must end
20 mm above the funnel!
» Assemble surface-mounted steam pipe input and insert in
fast connector (straight) down to the stop (approx. 28 mm).
» Optional concealed connection: Remove fast connectors
straight and 90° and insert 90° fast connectors on cold water
supply.
» The steam pipe must be conveyed across a drain funnel or
coil on installation.
18
|KA
3
2
1
9.4

Electrical connection

Electrical connections may be fastened to a permanently fitted
pipe only, using the built-in cable clip. The unit is designed for
an AC main and must be separable from the main with a break of
at least 3 mm all-pole, e.g. by fuses.
» Prepare electrical connection line.
» Connect up the unit in accordance with wiring diagram (see
chapter "Specification / Wiring diagram").
An on/off switch may optionally be installed by the
owner.
10. First start-up
Automatic start-up mode:
- Fill / Heat up periodically
- Total time approx. 24 min.
» Open cold water inlet to the unit.
» Switch on mains voltage.
The unit is automatically filled through the magnetic valve
and the heating process starts.
» Check connection tightness.
» Fit unit cover and fasten with 2 screws.
» Check unit operation.
ON lights up
- unit operative.
READY flashes
- automatic heating up up to boiling point (Time approx.
24 minutes). Automaticboiling point detection is undertaken.
- Do not draw water during boiling pointdetection as the proc-
ess will otherwiserecommence from the start (automatic).
READY lights up
- Boiling wateravailable
- Start-up mode has ended.
» Allow contents to run off (unit rinse).

11. Handing over the unit

» Explain unit operation to the user and familiarise with use.
» Point out possible risks to the user (scalding).
» Hand over these instructions for careful safekeeping.