Download Inhoudsopgave Inhoud Print deze pagina

Installation Example Bituminous Membrane (Floor Slab With Separating Layer) - Kessel Ecolift Inbouw- En Bedieningshandleiding

Inhoudsopgave

Advertenties

4.1.2

Installation example bituminous membrane (floor slab with separating layer)

1 Ecolift
2 Seal set art. no. 83073: extension
section with flange and mating
flange (for connection to an on-site
waterproofing sheet)
3 Extension section art. no. 83070
4 Cable conduit
a Floor covering
f Protective con-
crete
b Screed
g Control unit
c Insulation
h Pressure pipe
d Concrete floor
BWS* design
water level
e Waterproofing
layer
4.1.3
Maximum installation depth
A maximum installation depth of 650 mm to the top surface
of the functional unit (e.g. the pump) should be observed
for the installation in the floor slab. This way, the necessary
parts can be reached for maintenance and servicing.
Installation and operating instructions