√ Check whether the wires have been properly tightened, 4 to 5 Nm.
√ Check whether the cable thickness of the power cable matches the fused
current rating.
√ Check whether the charging station is tightly and properly secured.
√ Check whether the station is sufficiently waterproof.
√ Keep the immediate environment of the work area free from obstacles.
Before connecting the charging station to power, the back office provider must be
contacted to allow the software to be activated. The unique charging station number is
required for this.*
*Only applies to charging systems with registration
19. OPERATION / INSTALLATION MANUAL
19.1 Wall mounting
When the charger is mounted on a wall, the black mounting frame must be mounted to the
wall first, using the supplied bolts, before hanging and fixing the charger to the mounting
frame.
The perfect height of the charger is between 75cm and 95cm measured from the bottom of
the charger. (such that the cable holder is located at a height between 95cm and 115 cm)
Preferably the charger is not placed in a location in direct sun light.
19.2 Mounting on a frame
Installation of the foundation frame requires a hole of about L400 x W250 x D700 mm.
The power cable can be guided through the lower opening to the upper opening.
The (black) mounting frame must be removed first. This frame is not needed when the
station is mounted on the foundation frame. The bolts for the black mounting frame can be
used to mount the charger on the foundation frame.
See figures 1, 2, and 3.
Figure 1
20. www.ecotap.nl