Download Inhoudsopgave Inhoud Print deze pagina

Mandatory Checks Before Initial Use; User / Installation Manual; Mounting The Casing On The Foundation - LEGRAND ecotap Laadzuil Duo Wide Handboek

Inhoudsopgave

Advertenties

Beschikbare talen

Beschikbare talen

18. MANDATORY CHECKS BEFORE INITIAL USE

The following checks are mandatory before the charging station goes live.
NEVER use the charging station if one or more of the checks indicate that
the power supply or stability of the charging station does not suffice. Check
the insulation resistance of the various conductors in accordance with
NEN1010 provision 61.3.3.
Always perform the checks below before voltage is applied to the DUO
charging station.
√ All of the activities listed below must be performed in accordance with
NEN 3140.
√ Check whether the wires have been connected to the terminals in the right order.
√ Check whether the conductors on the terminals have been screwed on
properly (4 to 5 Nm).
√ Check whether the grounding connector has been connected to the
coded terminal and whether it has been connected to the grounding
electrode or the supplied grounding device. The entire grounding system
must comply with the NEN1010/EU/35.
√ Check whether the charging station is stable.
√ Check whether the seals on the charging station' s caps have been
installed properly during installation (IP54).
√ Check whether any actions still need to be performed, so that they may be
performed safely.
√ Make sure there are no obstacles surrounding the worksite.
√ Before any voltage is applied to the charging station, make sure to
contact Ecotap® B.V. by calling 0031 (0) 411-210210 so that we can
activate that particular station's software; we will need the station's
unique code to do so.

19. USER / INSTALLATION MANUAL

19.1 Mounting the casing on the foundation

The bottom of the hole (50x70 centimeters.) must be stable and levelled.
Place the foundation level in the hole and check with a spirit level.
Use 1 bag (20Kg) FAST-DRY CEMENT for the bottom of the foundation.
Place the charging station on the foundation without the 2 curved steel covers, and secure it
using the nuts and bolts supplied (nuts to the top).
Any slight discrepancy of the level can be corrected while closing the hole (using the soil that
was previously removed).
Covers can be removed by undoing 8 nuts on the inside of the charging station (top &
bottom to the side).
Take account of the connection face of the charging station in relation to walls, hedges, etc.
22. www.ecotap.nl
30-03-23

Advertenties

Hoofdstukken

Inhoudsopgave
loading

Gerelateerde Producten voor LEGRAND ecotap Laadzuil Duo Wide

Inhoudsopgave