6. LOCAL CONFIGURATION
The Home Advanced | Renault edition can be configured
locally using the installer wizard.
Two tools are required for local configuration:
1. Ethernet UTP cable
2. Laptop with RJ45 port
Make sure both the charge point and laptop are
powered for at least 5 minutes.
Install the configuration software. The installed program
will be refered as Installation Wizard.
- Connect the laptop to the Charge Point using a
standard UTP cable to the ethernet port
- Start the Installation Wizard
- Fill in the information requested in the tool
Press to find charger in the local network and select the
charge point which needs configuration. Always select &
perform firmware update when available.
6.1 POWER SETTING
Select the maximum allowed current for the installed
circuit. Taking into account the MCB, RCD, grid
connection and local regulations.
6.2 LOAD SHEDDING SETTING
Enable Load Shedding if upstream CT for 7,4 kW charge
point or Load Shedding module for 11 kW charge point
is installed.
When Load Shedding is enabled, fill in the maximum
current of the grid connection as the installation max
current.
6.3 ON/OFF PEAK SETTING
Enable ON/OFF Peak if smart meter is capable of
providing ON/OFF Peak output and is connected to the
charge point.
Set the maximum allowed current for charge sessions
during ON peak charging.
INSTALLATIEHANDLEIDING – P30
INSTRUCTION MANUAL – P30 | P30
6.4 START CHARGING SETTING
Set whether the charge session will be started
automatically after connecting the cable and car (default)
or using an RFID charge card.
6.5 TESTING
When Load Shedding data is received, a green light
shows in the wizard. Check if received data is correct.
Final test is the simulation for a welded relais. Press:
"Activate shunt". If the Charge Point is powered off, the
shunt is correctly installed.
Ensure that you finalize the SAT and save the
documentation for securing warranty.
Share the saved file with the customer.
VERSION 0129NM02INT01
0720NM19INT03
Laptop can be
connected via
router too